Roadmap

2018-2020
2018-2020

Design

• 2018: The first preliminary designs are drawn up

• 2022: The project was selected under the ADEME France 2030 call for projects

2023 - 2024
2023 - 2024

Construction

• 2023: Detailed engineering studies and obtaining the building permit for the industrial pilot site

• 2024: Construction of the industrial pilot plant using company funds, with commissioning in October

2025
2025

Industrialization

• Q1: The first volumes of syngas are produced at the industrial pilot plant

• Q2: The initial assumptions have been validated, and the facility enters the industrialization phase

2026
2026

Production

• Q1: NOVÉA has been selected under the GRDF call for projects (synthetic methane production)